Timeline

The fiscal year for the District is from October 1 to September 30.

Project Start: FY2023

2023 – 2025

Pre-Design:

  • Facility Population Projections
  • Architectual Programming
  • Stakeholder Engagement (ongoing)
  • Conceptual Design
  • Entitlement process

2025

Design Team & Construction Team Procurement

2025 – 2027

Design Finalization

2027 – 2031

  • Annex Building 1 Construction, Transition, & Activation
  • Existing CTF Renovations (separate project)

2029 – 2031

  • CDF Preparation for Construction of Annex Building 2
  • Demolition of CDF Admin

2031 – 2035

  • Annex Building 2 Construction, Transition, & Activation
  • Begin discontinuance of CDF use