Timeline

The fiscal year for the District is from October 1 to September 30.  References to quarters (Q1-Q4) in the project timeline correspond to this fiscal year as follows:

  • Q1 = October-December 
  • Q2 = January-March
  • Q3 = April-June
  • Q4 = July-September

Project Start: 2023

Q4 2023 – Q3 2024

Pre-Design:

  • Facility Population Projection
  • Site Selection
  • Programming
  • DOC Resident and Staff Surveys
  • Advocacy Group Surveys

 

Entitlements:

  • DC Zoning Commission
  • U.S. Commission of Fine Arts
  • National Capital Planning Commission

Q3 2024 – Q2 2026

Design

Q3 2024 – Q1 2025

Design and Construction Team Procurement Process

Q1 2027

Groundbreaking

Q1 2027 – Q3 2030

Sequence 1: Construction of Building 1 (Intake, Medical, Behavioral Health Housing & Admin Building); Existing CTF Renovations*

Q4 2029 – Q3 2030

Transition and Activation Process for Building 1 (Intake, Medical, Behavioral Health Housing & Admin Building)

Q2 2030 – Q1 2031

Prepare CDF Building for Construction of new Housing Building

Q1 2031 – Q3 2034

Sequence 2: Construction of Building 2 (New Housing Building; Begin discontinuance of CDF use)

Q2 2034 – Q4 2034

to Transition and Activation Process for New Complex

*Consolidation activities will be part of a separate, simultaneous CTF renovation project.